Determination of Schedule Line Category in SAP SD


Schedule line category:

In SAP SD process, schedule line category in sales order decides whether or how the system passes on requirements to materials requirements planning (MRP).


Determination:

Schedule line category is determined based on Item Category and MRP type


  • Item category is determined(sales document type + item category group + item usage + higher level item category) in sales order(screen 1.0)
  • MRP type is defined in material master - MRP 1(screen 1.1)


Screen 1.0





Screen 1.1

Determination Rule:

  1. Item Category + MRP type
  2. Item Category (if there is no MRP type defined), refer screen 1.2 for detail
This assignment is maintained in t-code VOV6(screen 1.2)